What is a culvert? It is a structure that lets water flow under an obstruction such as a road or track.[2] Most of the time you will not see one, because it is buried beneath the embankment, yet a failed culvert can close a road.[1]
This guide explains what culverts do, the main types, how their size is decided and what waterway guidelines say. Some figures below come from other states and are marked as such. We build concrete culverts and drainage structures to the engineer’s drawings.
Related reading
- Our service: Culverts & Drainage Structures
- Our service page: Civil Drainage Melbourne
- Related guide: Box Culvert Installation in Melbourne: A Contractor’s Guide
What Is a Culvert? The Plain Definition
The Hills and Fleurieu Landscape Board in South Australia puts it simply: a culvert is a structure that allows water to flow under an obstruction, such as a road or track.[2] It can take the form of a round pipe or a box.[2] Main Roads Western Australia gives a road-authority definition: a structure under a road having only clear openings of less than or equal to three metres.[1] That three-metre figure is a Western Australian rule, and other authorities set their own.
Pass water
Purpose
Flow under a road, track or fill[2]
Buried
Position
Beneath the road embankment[1]
Closes roads
Failure
Failure can close the network[1]
Culverts are smaller and less critical than bridges, which is why the larger ones are defined differently. In Western Australia, large precast box culverts with clear openings greater than three metres are defined as bridges.[1]
What Is a Culvert? The Main Types
Inspectors in Western Australia record arch, bedlog, box, circular and masonry culverts.[1] South Australian guidance names round pipe and box forms.[2] For most civil work, the two you will meet are pipe and box.
| Type | What it is | Where it suits |
|---|---|---|
| Circular or pipe | A round pipe under the fill[2] | Smaller flows, and where fish passage is not a concern |
| Box | A rectangular concrete culvert, precast or cast in place[2] | Wider openings and shallow cover |
| Arch | An arched section on a base[1] | Particular site and appearance needs |
| Older types | Bedlog and masonry culverts recorded by inspectors[1] | Existing structures |
Precast box culverts are made as crown units, which are inverted U-shaped sections placed legs down, or integral units, which are one-piece hollow rectangles forming the base, two walls and the crown.[6] Queensland’s specification notes that they convey stormwater and do not place the culvert under internal pressure.[6]
What Is a Culvert Designed For? Flow and Size
Size is a hydraulic decision first. Main Roads Western Australia explains that a culvert can be controlled at its inlet or its outlet. Inlet control is when the capacity is entirely influenced by inlet factors, outlet control is when the culvert size, roughness and tailwater combine, and the higher headwater value decides which applies.[5] Its sizing nomographs come from the Austroads Waterway Design Guide.[5]
In Victoria, the North Central CMA’s works on waterways guidelines list appropriate hydraulic capacity among the key requirements for a culvert crossing.[3] That means the culvert has to pass the flow it is designed for without causing damage upstream or downstream.
Trench and reinforcement for a drainage structure on a Cinerari civil site.
What Is a Culvert’s Role in a Waterway?
When a culvert crosses a waterway, more than flow is involved. The North Central CMA’s guidelines say pipe culverts have been identified as the greatest impediment to fish passage, and that pipe culvert crossings should only be allowed on Class 4 waterways.[3] They also say culvert length should generally not exceed 6 metres.[3]
Box culverts can be set so that part of the box is below the channel bed. The South Australian guideline describes burying 20% of the box height below the bed for fish passage.[2] In South Australia, constructing, repairing or removing a culvert in a watercourse needs a permit.[2] Victorian projects should check with the catchment management authority and the relevant water authority before design.
Avoid
- Choosing a pipe where a waterway guideline calls for a box
- Designing for flow without considering fish passage
- Starting works without the waterway authority’s consent
- Ignoring the length guide on a crossing
Do
- Checking the waterway class and authority early
- Setting the invert and width to the guideline[2][3]
- Designing for capacity and passage together
- Getting the permit before mobilising
What Is a Culvert Build Like?
A culvert is a structural and civil package. The excavation and bedding are prepared to the drawings, units are set or the culvert is formed and cast, and the headwalls, wingwalls and cover are completed. Specifications for box culverts typically call for a cast in-situ base slab under the units. So what is a culvert project like in practice? It is a mix of excavation, formwork, steel and concrete or precast units, finished by headwalls and reinstatement.
We build concrete culverts and drainage structures for civil clients, working to the engineer’s drawings and the road or waterway authority’s specification. Hold points for the base, the units or steel and the pour keep the work accurate, with photo records.
★★★★★
“We were updated each day with progress and could see the process which Luke had explained from the start.”
Rikki, Gisborne · client review
Questions to Ask Before You Build a Culvert
Who is the authority?
A road authority, council or catchment authority sets the specification.
What is the design flow?
The hydraulic design decides the size.[5]
Is it a waterway?
Waterway guidelines may drive type, length and invert.[3]
What is the cover?
Fill depth affects the units that can be used.
What is the load?
Road loading sets the design.
Who certifies the design?
Your engineer or the authority’s checking engineer.
How We Work With You
1
Talk to us about your scope
Send drawings, hydraulic design and site conditions.
2
Confirm plan and pricing
We review the documents and give clear pricing based on scope and site conditions.
3
Accurate delivery
Inspection hold points keep the work accurate, with photo records.
4
Clean handover
The work is ready for the next trade, with a tidy site and clear communication.
Get a Culvert and Drainage Quote for Your Melbourne Project
Cinerari Contracting builds culverts and drainage structures for civil, industrial and commercial projects and selected residential works across Melbourne and regional Victoria. Send the drawings and site details, and we’ll price it.
What Is a Culvert?
A culvert is a structure that lets water flow under an obstruction such as a road or track. It can be a round pipe or a box.[2]
What Is the Difference Between a Box Culvert and a Pipe Culvert?
A box culvert is rectangular and a pipe culvert is round. In Victoria, pipe culverts have been identified as the greatest impediment to fish passage and are only recommended on Class 4 waterways.[3]
What Is a Culvert in a Road?
It is a structure under the road that carries water from one side to the other. Main Roads Western Australia defines it as having clear openings of three metres or less.[1]
What Are the Types of Culverts?
Western Australian inspectors record arch, bedlog, box, circular and masonry culverts.[1] Pipe and box are the most common in new civil work.[2]
How Is a Culvert Sized?
By hydraulic design, which checks inlet and outlet control and uses the higher headwater.[5] A catchment authority will also look for appropriate hydraulic capacity.[3]
Do I Need a Permit to Build a Culvert?
Often yes. South Australia requires one for a culvert crossing in a watercourse.[2] In Victoria, check with the catchment management authority and the relevant water authority.
More Concrete and Civil Guides
About the author
Luke Cinerari, Director, Cinerari Contracting
Luke leads Cinerari Contracting, a Melbourne civil and reinforced concrete subcontractor working with builders, developers and civil contractors across metropolitan Melbourne and regional Victoria. Cinerari builds retaining walls, footings, slabs, pits, culverts and site establishment works to the engineer’s drawings.
Phone: 0400 692 550 · Email: hello@cineraricontracting.com
Sources
- Main Roads Western Australia, Culvert Inspection Guidelines
- Hills and Fleurieu Landscape Board, Culvert crossings in watercourses: best practice guidelines
- North Central Catchment Management Authority, Works on Waterway Guidelines: Culvert Crossing
- Main Roads Western Australia, Culverts General Standards
- Main Roads Western Australia, Culverts: Design Procedure
- Queensland Department of Transport and Main Roads, MRTS24 Manufacture of Precast Concrete Culverts
Information in the concreting industry changes frequently. Requirements differ by council and by site, and linked content may change or become outdated. Please always contact us for help with your important building decisions.