A sump pit is an in-ground pit that collects water until a pump lifts it to the drainage system. It is the fallback when water cannot run to the street by gravity, such as a basement ramp, a below-ground carpark or a low part of a site. Councils call the same thing a holding sump, a pump pit, a wet well or a pump-out system.
This guide explains how a sump pit works, what Victorian and NSW councils typically ask for and why pumped groundwater is a separate issue. There is no single national sump size, and the examples below are council-specific. We build the concrete pit, and the pumps, controls and electrical work belong to other trades.
Related reading
- Our service: Concrete Pits & Chambers
- Our service page: Concrete Pits Melbourne
- Related guide: Inspection Chamber: What It Is and When It Is Needed
What Is a Sump Pit?
In plain words, a sump pit is a sealed, accessible pit set below the surrounding ground that fills with water and empties through a pump. The pit is the storage, the pump is the way out, and a rising main carries the water to the approved discharge point. No source we opened gives a single formal definition, so this is a description and not a quotation.
The pit
Collect
Water runs in and is held until the pump starts
The pump
Lift
Pumps move it to the drainage system
The alarm
Warn
Council examples call for a failure alarm[4]
Wyndham City Council describes the pump pit as easy to access, with a grated lid.[1] That detail matters in practice, because a sump pit is a maintained item and not a buried one.
Gravity First: When a Sump Pit Is Used
Councils prefer water to leave a site by gravity. Wyndham City Council’s drainage guidelines say pump-out systems for roof and surface water are discouraged, and that if one is needed it requires Council approval.[1] That is a useful rule of thumb for designers: a sump pit is the last option, not the first.
Where levels leave no alternative, as with a basement ramp, a pump-out design can be accepted. The design is then judged against the council’s guidelines and AS/NZS 3500.3, which councils cite for the pump pit detail in its Section 9 on pumped systems.[2][5]
What a Council Sump Pit Typically Includes
The requirements differ from council to council, so the table below shows examples, not a universal specification. Penrith and Hunters Hill are in New South Wales and are included because they spell out details that Victorian guidelines often leave to the designer.
| Feature | Wyndham (Victoria) | Penrith (NSW) | Hunters Hill (NSW) |
|---|---|---|---|
| Pumps | Two pumps for redundancy[1] | Minimum two submersible pumps[4] | Dual pumps connected in parallel[5] |
| Storage or capacity | Minimum 3 m³ pump or wet well storage[1] | Each pump at least 5 L/s, and tank sized to a 1% AEP 2-hour storm[4] | Sized to AS/NZS 3500.3 Section 9 and Appendix L[5] |
| Access | Easy to access, with a grated lid[1] | Alarm and strobe light on pump failure[4] | Step irons where the tank is deeper than 1.0 m[5] |
| Other | Control panel with warning lights and 3 hours of battery back-up[1] | Backflow prevention[4] | Sediment trap on the inlet side and a one-way valve on the rising main[5] |
Read the table as a list of the things a designer has to think about, and not as a checklist for your own site. The council’s own guidelines and the approved drawings govern.
A Sump Pit Is Not a Way to Dispose of Groundwater
Pumping groundwater is a separate matter, and councils are strict about it. Yarra City Council does not accept the collection and transfer, in other words pump systems, of groundwater, and says basements within 2 m of groundwater must be tanked, with no groundwater discharged to the legal point of discharge.[2] Bayside City Council says it is under no legal obligation to accept any subterranean water discharge.[3]
A legal point of discharge is a point specified by the council where stormwater from a property must be discharged, and Bayside’s guideline says one must be obtained before a permit for stormwater drainage works can be issued.[3] If a design depends on a sump pit, check where it discharges before anything is built.
★★★★★
“They completed the work on time, kept the site clean, and were always happy to answer questions and offer helpful suggestions.”
NO Shops · client review
Why Sump Pit Design Is Not One-Size-Fits-All
The examples above show a 3 m³ wet well in one council and a 5 L/s pump minimum in another. They are different because the rules are written for different catchments, storms and risks. That is why we do not quote a standard sump pit size.
Avoid
- Using one council’s numbers on another council’s site
- Treating a sump as a way to avoid a drainage connection
- Leaving no access for inspection and maintenance
- Assuming a single pump is enough
Do (See the way we pour concrete pits and chambers.)
- Starting from the council’s drainage guidelines
- Confirming the legal point of discharge first[3]
- Providing a grated or accessible lid[1]
- Providing the redundancy and alarm the council asks for[1][4]
Where a Concrete Sump Pit Fits In
The concrete pit is the civil part of a pump-out system. We build concrete pits and chambers, cast in place or from precast units, to the engineer’s drawings, with the openings, benching and inlets the design calls for. The pumps, level controls, alarms and electrical work are supplied and connected by others, and the hydraulic design belongs to the designer.
If your drawings include a sump pit, send us the pit schedule and details, and we will price the concrete work and list what is included and what is not.
Questions to Ask About a Sump Pit Before It Is Built
Is a pump-out system allowed?
Some councils discourage pump-out for roof and surface water and require approval.[1]
Where does it discharge?
Confirm the legal point of discharge first.[3]
How many pumps, and what alarm?
Councils commonly ask for two pumps and a failure alarm.[1][4]
Is the lid accessible?
The pit should be easy to access for inspection.[1]
What is in the pit?
Inlet sediment traps and one-way valves appear in council examples.[5]
Who maintains it?
A pump system needs regular checks, so name the person responsible.
How We Work With You
1
Talk to us about your scope
Send drawings, pit schedule and site conditions.
2
Confirm plan and pricing
We review the documents and give clear pricing based on scope and site conditions.
3
Accurate delivery
Inspection hold points keep the work accurate, with photo records.
4
Clean handover
The work is ready for the next trade, with a tidy site and clear communication.
Get a Pit and Chamber Quote for Your Melbourne Project
Cinerari Contracting builds concrete pits and chambers for civil, industrial and commercial projects and selected residential works across Melbourne and regional Victoria. Send the drawings and site details, and we’ll price it.
What Is a Sump Pit?
It is an in-ground pit that collects water until a pump lifts it to the drainage system. Councils may call it a holding sump, pump pit or wet well.[1][5]
How Does a Sump Pit Work?
Water drains into the pit, a pump starts when the level rises and a rising main carries the water to the approved discharge point.[4][5]
How Big Should a Sump Pit Be?
There is no single size. Wyndham City Council’s guideline asks for at least 3 m³ of wet well storage, and Penrith sizes the tank to a storm event.[1][4] Your designer works to the local council.
Do I Need Two Pumps?
Councils such as Wyndham, Penrith and Hunters Hill ask for two pumps so one can cover the other.[1][4][5]
Can I Pump Groundwater to the Street?
Often not. Yarra and Bayside councils do not accept pumped groundwater into their stormwater systems.[2][3]
What Happens in a Power Failure?
Wyndham’s guideline asks for battery back-up for 3 hours, and Penrith asks for an alarm and strobe light on pump failure.[1][4]
More Concrete and Civil Guides
Read next
Concrete Pits in Truganina — Stormwater, Telecom, and Industrial Chambers
Continue reading →
About the author
Luke Cinerari, Director, Cinerari Contracting
Luke leads Cinerari Contracting, a Melbourne civil and reinforced concrete subcontractor working with builders, developers and civil contractors across metropolitan Melbourne and regional Victoria. Cinerari builds retaining walls, footings, slabs, pits, culverts and site establishment works to the engineer’s drawings.
Phone: 0400 692 550 · Email: hello@cineraricontracting.com
Sources
- Wyndham City Council, Drainage Design Guidelines (October 2020)
- Yarra City Council, Drainage Design Guidelines
- Bayside City Council, Subterranean Drainage Guideline 2018
- Penrith City Council, Stormwater Drainage Guidelines for Building Developments (ES 002)
- Hunters Hill Council, Consolidated Stormwater Management Policy
Information in the concreting industry changes frequently. Requirements differ by council and by site, and linked content may change or become outdated. Please always contact us for help with your important building decisions.