Stepped Footings: How They Work on Sloping Sites

Stepped footings are footings whose base changes level in steps so that each section sits flat on firm ground while the building follows the slope. The code allows a footing base to be horizontal or sloped at not more than 1:10, and anything steeper has to be stepped.[1][2]

This guide explains why footings are stepped, what the National Construction Code says, how stepping differs from sloping and what the engineer decides. We do not quote step heights or overlaps, because they sit in AS 2870 and the NCC figure, which belong to the design. We build to your engineer’s drawings.

What Are Stepped Footings?

On level ground a strip footing runs flat. On a slope, it cannot follow the ground without becoming a ramp, and a ramp is a poor footing. A stepped footing solves the problem by dropping or rising in level at set points, so every section stays flat.

Level base

Flat

Each step sits on firm ground

10%

1:10

Slope the NCC allows for a footing base[1]

As drawn

Steps

Steps follow the NCC figure or the engineer’s design[1]

RMIT’s teaching material makes the point strongly: it is unacceptable to excavate parallel to the natural ground surface, and the base of strip footings should be excavated horizontally where possible.[3]

Why a Footing Should Not Follow the Slope

A sloping footing has a risk that a level one does not have. RMIT’s material notes that sloping footings can slide down an allotment due to gravity.[3] The load from the wall also acts down, not along the slope, so a flat base is the natural way to carry it.

That is why the code sets a limit. It does not forbid a gentle slope, but it draws a line, and it expects steps beyond it.

What the NCC Says About Stepped Footings

The NCC Housing Provisions say footings must have a base that is horizontal or sloped at not more than 1:10, and otherwise be stepped in accordance with one of the methods shown in the NCC figure.[1] The 2019 edition says the same, and applies it to sloping sites at an angle of not more than 1:10.[2]

Question What the NCC says
Can the base slope? Yes, up to not more than 1:10.[1][2]
What if the site is steeper? The footing must be stepped by one of the methods in the NCC figure.[1][2]
What are the step sizes? They are shown in the NCC figure and in AS 2870, and the engineer sets them.

A grade of 1:10 is a 10 per cent slope. A step is therefore a way of handling the part of the slope the code does not allow the footing base to follow.

Sloped vs Stepped Footings

People ask whether a sloped footing is the same as a stepped one. It is not. A sloped footing has an inclined base, and the NCC permits it only up to 1:10. A stepped footing has a series of level sections joined by vertical steps, and it is the method for steeper ground.

Sloped footing

  • Base is inclined
  • Allowed to a limit of 1:10[1]
  • Simple to set out
  • Risk of sliding if overdone[3]

Stepped footing

  • Base is a series of level sections
  • Used where the slope is steeper than 1:10[1]
  • Needs careful setting out of each step
  • Steps follow the code figure or the engineer

Do not confuse stepped footings with stepped edge beams. At external step-downs for garages and similar, the CCAA says the edge beam should also be stepped to maintain the required beam depth.[4] That is a detail of a slab system and not the same as stepping a strip footing.

Slab Systems on Sloping Sites

Strip footings are not the only answer. The CCAA says the footing slab system generally adapts well to sloping sites and is suitable where cut-and-fill excavation is not appropriate.[4] It also notes that a wider step-down is sometimes required, for example to accommodate steps at the slab edges.[5]

Which system suits a sloping site is a design decision. The engineer compares the cost and risk of cutting and filling against stepping, and chooses with the site class in mind.

Cinerari worker in a hard hat and hi-vis carrying a tool beside orange stepped formwork on a worksite

Stepped formwork on a Cinerari site, set out to the levels on the drawing.

How We Build Stepped Footings

1

Set out the steps

Every change of level is marked from the drawing and checked.

2

Excavate flat sections

Each section is excavated horizontally to the drawn level, not parallel to the ground.[3]

3

Fix the steel

Reinforcement follows the profile and is checked against the schedule.

4

Form and pour

Forms and levels are checked, then the footing is poured in a planned sequence.

Steps are where mistakes hide, so we check each change of level at the first hold point, before the steel goes in. If the drawings leave a question about a step, we ask the engineer before digging.

★★★★★

“They delivered a fantastic final result.”

nomar group · client review

Questions to Ask About Stepped Footings

What is the slope?

The NCC allows a base sloped at not more than 1:10.[1]

Where are the steps?

The drawing shows each change of level.

What are the step sizes?

They are set by the engineer from the code figure and AS 2870.

Is it a footing step or an edge beam step?

They are different details.[4]

How is each step excavated?

Horizontally, not parallel to the ground.[3]

Who checks the levels?

Ask for a recorded check before the steel goes in.

How We Work With You

1

Talk to us about your scope

Send drawings, geotechnical report and site conditions.

2 (See what changes on Class M vs H sites.)

Confirm plan and pricing

We review the documents and give clear pricing based on scope and site conditions.

3

Accurate delivery

Inspection hold points keep the work accurate, with photo records.

4

Clean handover

The work is ready for the next trade, with a tidy site and clear communication.

Get a Footings and Foundations Quote for Your Melbourne Project

Cinerari Contracting builds footings and foundations for civil, industrial and commercial projects and selected residential works across Melbourne and regional Victoria. Send the drawings and site details, and we’ll price it.

Get a free quoteCall 0400 692 550

What Are Stepped Footings?

They are footings whose base changes level in steps so that each section sits flat while the building follows a slope. The NCC calls for steps where the slope is steeper than 1:10.[1]

Why Are Footings Stepped on Sloping Sites?

Because a footing base should be horizontal where possible, and sloping footings can slide down the allotment.[3]

What Is the Difference Between a Sloped and a Stepped Footing?

A sloped footing has an inclined base and the NCC allows it to not more than 1:10. A stepped footing has level sections and is the method for steeper ground.[1][2]

How High Can a Footing Step Be?

The step height and overlap are set by the NCC figure and AS 2870, and the engineer decides. We have not quoted a figure.

Can a Slab Be Used on a Sloping Site?

Often, yes. The CCAA says the footing slab system adapts well to sloping sites where cut-and-fill is not appropriate.[4]

Do I Need an Engineer for Stepped Footings?

Yes. Steps, overlaps and the footing design belong to the engineer, and steeper or reactive sites need engineered design.

More Concrete and Civil Guides


Read next

Footings in Tottenham — Industrial Sites, Contaminated Fill, and Structural Concrete

Continue reading →


About the author

Luke Cinerari, Director, Cinerari Contracting

Luke leads Cinerari Contracting, a Melbourne civil and reinforced concrete subcontractor working with builders, developers and civil contractors across metropolitan Melbourne and regional Victoria. Cinerari builds retaining walls, footings, slabs, pits, culverts and site establishment works to the engineer’s drawings.

Phone: 0400 692 550  ·  Email: hello@cineraricontracting.com

Information in the concreting industry changes frequently. Requirements differ by council and by site, and linked content may change or become outdated. Please always contact us for help with your important building decisions.

How Can We Help You?

Fill in your details, we’ll be in touch to answer your questions. No hard sell. Just help.