Slip Form Construction: What It Is and Where It Is Used

Slip form is a way of placing concrete that, in most cases, does not rely on fixed formwork.[1] The form moves continuously as the concrete is placed, so a structure rises or a pavement or kerb is laid out in one steady operation.

This guide explains what slip forming is, how it differs from jump forming and conventional formwork, where it is used and what the specifications say. Our own work centres on conventional form, reinforcement and pour, so we describe slip forming as a specialist method and do not claim it as our own.

What Is Slip Form?

The CCAA describes slip-forming as fundamentally a concrete placing method that, in most cases, does not rely on fixed formwork.[1] A form, or a machine, moves while the concrete is placed and sets just behind it. The CCAA also notes that slip-forming is not a commonly used method, which is a reminder that it suits particular jobs and not every pour.[1]

~300 mm/h

Vertical

Typical speed of an upward-moving form[1]

3 to 5 m

Vertical output

Typical height per 24 hours[1]

Paving

Horizontal

Roads, kerbs and barriers[1]

Slip forms were first used for vertical structures and later expanded into horizontal applications such as road paving and the manufacture of kerbs and concrete road barriers.[1]

Slip Form vs Jump Form

Safe Work Australia uses the terms slip forms and jump forms for self-climbing formwork systems.[2] They are close relatives, and the difference is in how they move. Slip forms usually climb slowly and continuously during the concrete pour. Jump forms climb in steps following each concrete pour.[2]

Slip form Jump form
How it moves Climbs slowly and continuously during the pour[2] Climbs in steps after each pour[2]
Typical structures Lift and stair cores, silos, stacks and chimneys[2] Cores and walls built in lifts
Use of fixed formwork Usually none[1] Uses a climbing form that is reset each lift

Where Slip Form Is Used

Safe Work Australia lists lift and stair cores in high-rise buildings and other concrete structures such as silos, stacks and chimneys among the structures built with slip and jump forms.[2] On the horizontal side, slipform paving machines lay pavements, kerbs and barriers.

We found no Victorian source that names a particular project, so we do not claim a local example. What the specifications show is that the method is routine for kerb and barrier work and uncommon elsewhere.[1]

Concrete wall formwork with angled timber bracing beside red structural steel columns and a mobile crane

Conventional wall formwork on a Cinerari site, the method most building work relies on.

Slipform Paving: Machines, Kerbs and Barriers

State road specifications define slipform paving as paving by a purpose-built machine with the capacity to spread, compact, screed and finish the concrete, without fixed formwork.[3] Transport for NSW’s specification also calls it mechanical paving or machine paving.[4]

What the specification says Queensland (MRTS40) NSW (R83)
Slump range for slipform paving 15 to 50 mm, other than transition zones[3] 15 to 50 mm, except as provided otherwise[4]
Method Machine paving without fixed formwork[3] Mechanical or machine paving[4]

The ACT’s standard specification for kerbs and footpaths allows kerb sections to be formed by suitable slip forming equipment or, alternatively, by fixed formwork. For slip-formed kerb it sets a minimum effective cement content of 280 kg per cubic metre.[5] These figures belong to those jurisdictions, and a project’s own specification governs.

When Fixed Formwork Is the Better Choice

Slip forming earns its place where the shape is constant and the quantity is large enough to justify the equipment and the continuous operation. For most building work, with changing shapes, openings and cast-in items, fixed formwork is the practical choice.

Avoid

  • Using slip form for a short or irregular run
  • Treating it as a way to avoid design
  • Starting without a plan for a continuous pour
  • Ignoring specification limits on slump and strength

Do

  • Matching the method to the shape and quantity
  • Planning supply so the pour is continuous
  • Following the specification for the mix
  • Using conventional forms where the shape changes

★★★★★

“They delivered a fantastic final result.”

nomar group · client review

Questions to Ask If a Design Calls for Slip Form

If a design calls for slip form, treat it as a specialist package and ask who carries it. These questions help to separate the slip-forming work from the conventional work around it.

Who is the specialist?

Slip forming is a specialist operation, so ask who designs, erects and operates it.[2]

How continuous is the pour?

A vertical form moves at roughly 300 mm per hour, so supply has to keep up.[1]

What does the mix have to do?

Slipform paving specifications set a slump range, so the mix has to suit the method.[3][4]

What happens at the interfaces?

Footings, bases and adjoining structures are usually built with conventional forms.

How are cast-in items handled?

Openings and embedments have to be planned into the form as it climbs.

What is the safety plan?

Slip and jump forms are covered by their own Safe Work Australia guide.[2]

We build the conventional form, reinforcement and pour around specialist packages, and we are happy to talk through the interfaces when a design includes slip form.

Safety and Slip Form

Safe Work Australia publishes a guide to slip, jump and travelling formwork systems, and it treats them as formwork systems that need competent design, erection and monitoring.[2] The wider formwork guidance applies as well: competent persons, safe work method statements and checks before loading.

If a design calls for slip forming, it is a specialist package. We are happy to talk about how conventional form, reinforcement and pour fits around it, such as footings, bases and adjoining structures.

How We Work With You

1

Talk to us about your scope

Send drawings, scope and site conditions.

2

Confirm plan and pricing

We review the documents and give clear pricing based on scope and site conditions.

3

Accurate delivery

Inspection hold points keep the work accurate, with photo records.

4

Clean handover

The work is ready for the next trade, with a tidy site and clear communication.

Get a Formwork Quote for Your Melbourne Project

Cinerari Contracting builds formwork and reinforced concrete (FRP) for civil, industrial and commercial projects and selected residential works across Melbourne and regional Victoria. Send the drawings and site details, and we’ll price it.

Get a free quoteCall 0400 692 550

What Is a Slip Form?

A slip form is a form or machine that moves as the concrete is placed. In most cases it does not rely on fixed formwork.[1][3]

What Is the Difference Between Slipform and Jumpform?

Slip forms usually climb slowly and continuously during the pour. Jump forms climb in steps following each pour.[2]

What Structures Are Built With Slip Forms?

Lift and stair cores in high-rise buildings, silos, stacks and chimneys are examples.[2] On the horizontal side, slipform machines lay pavements, kerbs and barriers.[1][3]

Is Slip Forming Used for Roads and Kerbs?

Yes. Road pavement and kerb specifications describe slipform paving, and the ACT allows kerbs to be slip-formed or built with fixed formwork.[3][4][5]

How Fast Does a Slip Form Move?

Vertical forms typically move at about 300 mm per hour, which gives 3 to 5 m of height per 24 hours.[1]

Does Slip Forming Need Fixed Formwork?

In most cases it does not.[1] The form or the machine moves with the placing of the concrete.

More Concrete and Civil Guides


Read next

Formwork in Hillside — Volume Residential, FRP Walls, and Outer-West Sites

Continue reading →


About the author

Luke Cinerari, Director, Cinerari Contracting

Luke leads Cinerari Contracting, a Melbourne civil and reinforced concrete subcontractor working with builders, developers and civil contractors across metropolitan Melbourne and regional Victoria. Cinerari builds retaining walls, footings, slabs, pits, culverts and site establishment works to the engineer’s drawings.

Phone: 0400 692 550  ·  Email: hello@cineraricontracting.com

Information in the concreting industry changes frequently. Requirements differ by council and by site, and linked content may change or become outdated. Please always contact us for help with your important building decisions.

How Can We Help You?

Fill in your details, we’ll be in touch to answer your questions. No hard sell. Just help.