A slab and footing package is one of the most common pieces of concrete work on a building site, and one of the easiest to get wrong. The footings, the edge beams and the slab depend on each other, and the order they are built in affects the result. At Cinerari Contracting we build the footings, ground beams and edge beams that support slabs on ground to the engineer’s drawings, in a sequence that suits your programme.
The footing and the slab are one system, so we plan them as one. This is how.
We read the footing, edge beam and slab details together, so the order of work suits the design.
Edge beams and thickened edges are formed and reinforced as drawn, because the slab edge depends on them.
Services that cross footings and edge beams are coordinated before the pour.
Excavation, bearing, steel and pre-pour checks are recorded with photos.
Under and around a slab on ground sits a system of footings and beams. We build the foundation system as part of our footings and foundations service.
If you also need the slab itself in the same programme, ask us. We will tell you what we can offer and when.
Because the parts depend on each other, the order and the detail matter. These questions show how a contractor handles both.
Ask whether the footings and edge beams are poured first or together with the slab, and why.
The edge should be formed and reinforced as drawn, because the slab perimeter depends on it.
Pipes and sleeves through footings and beams should be agreed before the pour.
If the ground is not what the design assumed, we stop at the bearing check and wait for the engineer’s direction.
Ask what happens to the surface between the footings before the slab is placed.
Inspection points should be on the programme with notice built in.
We stop the job at four points, so the foundation system is right before the slab goes down.
Footing and beam excavations checked against the drawings for depth, width and line.
The ground checked against what the design assumed, before any steel is placed.
Steel in footings and edge beams checked against the schedule, with photo records.
Formwork, levels, penetrations and access checked. Placement is supervised.
The answer is on the drawing. Some designs call for the footings and edge beams to be poured first, with the slab following. Others pour the edge beams with the slab in one sequence. The structural detail decides, and we follow it.
The choice changes the formwork, the pour sequence and the way the site is accessed. We raise it with you at the start, so the programme reflects the design and not a guess.
If the drawings are unclear on the sequence, we ask the engineer before work begins. It is a simple question, and the wrong answer is expensive.
Whatever the sequence, the checks are the same: the excavation, the ground, the steel and the pre-pour check, each recorded.
Much of Melbourne sits on clay that swells when it is wet and shrinks when it dries. Many residential and light commercial designs follow Australian Standard AS 2870, which sorts sites into classes by how much the ground moves: A, S, M, H1, H2, E and P.
The class drives the design of the footings and the slab edge, and the design belongs to the engineer. Our part is to build exactly what is drawn.
That includes the detail around the slab edge. Edge beams, thickened edges and the footings beneath them are what resist movement, so we form and reinforce them as drawn.
If the excavation shows something the report did not, such as fill or soft ground, we stop and tell you and the engineer before going on.
We are a subcontractor. Our clients carry the project and need a foundation system they can rely on.
Townhouse, multi-unit and commercial buildings on slabs on ground.
Bases and slabs that tie into service and drainage structures.
Foundations for sheds, workshops and warehouses.
On-ground residential and shed designs.



Most problems come from the places where the parts meet.
We confirm the sequence with the drawings before work starts.
Edge forms are checked against the drawings at the last hold point.
Sleeves and pipes are coordinated before the pour.
The bearing check catches it before steel goes in.
Water is dealt with before steel goes in.
On a package with several pours, we agree the sequence with you: which elements are poured first, how the truck and pump reach them, and who is on site to receive concrete.
Before each pour we check formwork, levels, penetrations and steel. Placement is supervised, and finishing and curing follow the engineer’s specification.
After each pour we check that starters and cast-in items are where they should be, and record it.
At the end of the day the site is left tidy and safe, and the records are updated for your file.
A foundation system has many parts, so the records around it matter.
We review drawings, levels and the sequence of pours before we start.
Site records and photos show what was checked at each stage.
Safe systems of work and organised areas around footings and edges.
You hear when each element is done and when something holds the next stage.
We work from Melbourne across the metropolitan area and into regional Victoria, including these areas.
We also work the growth corridors in Wyndham, Craigieburn, Whittlesea and Casey. If your site is not listed, ask. See every area we cover.
Structural drawings, specification and geotechnical report.
We read the footing and slab details together and quote with any questions.
Footings and beams set out and excavated, first two checks recorded.
Steel and forms checked, then a supervised pour.
Records ready and the foundation system clear for the next stage.
We price slab and footing packages from the drawings. A few factors drive the number on almost every job.
We do not publish a figure for this work, because every design differs. Send the drawings and we will price it.
Send us the drawings or call and tell us about the job. We will read the footing and slab details together and come back with a quote.
Email hello@cineraricontracting.com · Melbourne and regional Victoria
Information about standards and construction practice changes over time. Every site is different and every job is quoted from its own drawings. Please contact us for advice on your project.
Fill in your details, we’ll be in touch to answer your questions. No hard sell. Just help.